Tier-1 bank executive boardroom commission requiring 280 sqm specification-grade walnut hardwood across the full boardroom plus directors' reception corridor. Floor Experts Ghana coordinated hardwood-grade selection from NWFA NOFMA Premier grade, hand-honed edge profiling, and architect-coordinated installation against an active banking-floor schedule.
Project Profile
| Field | Detail |
|---|---|
| Sector | Premium Office Fit-Out — Financial Services |
| Scale | 420 sqm across boardroom, executive reception, and adjoining corridor suite |
| Scope | Full subfloor preparation, engineered hardwood installation, acoustic underlay system, LVT specification for ancillary corridors, snagging and sign-off |
| Timeline | 6 weeks — phased to protect active banking operations on adjacent floors |
A Tier-1 bank occupying a prestige address in Accra’s Ridge District commissioned a complete flooring replacement across its executive boardroom and senior leadership suite. The brief was unambiguous: the floor had to carry the visual weight of a boardroom where governance decisions are made, hold up under continuous institutional foot traffic, and meet the acoustic standards a confidential deliberation environment demands.
Specification Challenge
Ridge District addresses impose a particular discipline. Heritage building fabric — ageing screed, minor differential settlement, embedded services dating to an earlier construction phase — frequently presents subfloor conditions that cannot simply be overlaid. Initial assessment revealed levelness deviations of up to 9mm across the boardroom footprint, screed delamination in two zones adjacent to the window wall, and moisture readings inconsistent with direct hardwood bonding.
Beyond substrate, the acoustic specification was non-negotiable. A boardroom operating at this tier cannot afford flutter echo or impact transmission to floors above and below. The acoustic underlay had to perform across both wood and LVT zones without creating a visible transition inconsistency at the threshold.
Approach
Floor Experts Ghana’s site specialists conducted a full moisture-mapping survey and levelness audit before any materials were brought to site. Remediation proceeded in sequence: delaminated screed sections were mechanically removed, self-levelling compound was applied across the full boardroom field, and moisture suppression primer was allowed full cure time before the installation programme began.
The boardroom and executive reception received specification-grade engineered hardwood — a 189mm wide-plank European oak, site-finished in a satin oil system compatible with the bank’s interior design specification. A high-density acoustic underlay rated to 19dB impact sound reduction was installed beneath the full hardwood field.
Adjoining corridors and the executive reception transition zone were specified in luxury vinyl tile (LVT) — a stone-effect plank in 600×300mm format, glue-down method, providing the durability and maintenance profile a high-traffic corridor demands while holding design coherence with the boardroom threshold.
All installations were completed under manufacturer-warranted installation protocols. Phasing was agreed with the client’s facilities management team to ensure no disruption to live banking floors.
Outcome
- Subfloor levelness achieved to ±2mm across the full 420 sqm field before installation commenced
- Acoustic performance of the boardroom met the specified 19dB impact sound reduction target
- Engineered hardwood and LVT transition managed within a single threshold detail — no step, no visual discontinuity
- Full programme delivered within the 6-week window, with zero disruption to adjacent occupied banking operations
- Manufacturer warranty activated on both hardwood and LVT systems at practical completion
What This Project Demonstrates
Financial services boardrooms represent the most specification-demanding category within premium office fit-out. Substrate remediation, acoustic performance, and phased delivery under live-building constraints require a level of pre-installation discipline that separates specification-grade practice from volume installation.
Established 1978, Floor Experts Ghana has delivered specialty floors across this sector for 48 years. The Ridge District boardroom reflects a pattern consistent across Tier-1 institutional office mandates: rigorous subfloor preparation is never optional — it is the foundation on which every warranty and every performance claim rests.